NEW QUESTION 86
In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?
Please choose the correct answer.
Response:
- A. Deploy
- B. Prepare
- C. Explore
- D. Realize
Answer: C
NEW QUESTION 87
When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
Response:
- A. During each Firm-up Sprint
- B. Before Integration Testing
- C. After each Sprint
- D. After Integration Testing
Answer: D
NEW QUESTION 88
How do you set up Scrum teams?
There are 2 correct answers to this question.
Response:
- A. Based on End-to-End Processes like Order-to-Cash
- B. By type of work, like configuration Scrum, documentation Scrum, and testing Scrum.
- C. Based on group size, but a minimum of 12 people
- D. As a cross-functional team covering multiple functions, like configuration, data loads, and testing
Answer: A,D
NEW QUESTION 89
What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices?
Please choose the correct answer.
Response:
- A. Activate and apply SAP Best Practices with SAP Solution Manager
- B. Assemble and apply SAP Best Practices to the system
- C. Activate and apply SAP Best Practices content with the self-service configuration UI
- D. Apply SAP Best Practices with the Configure your Solution application
Answer: A
NEW QUESTION 90
Which tool can you use to collaborate with other SAP Activate methodology practitioners?
Please choose the correct answer.
Response:
- A. SAP Implementation Assistant
- B. SAP Solution Manager
- C. Roadmap Viewer
- D. SAP Jam
Answer: D
NEW QUESTION 91
Which end-to-end turn-key Application Lifecycle Management (ALM) solution can support you in managing requirements and software development for large, Agile projects?
Please choose the correct answer.
Response:
- A. Focused Build
- B. Change Request Management
- C. Requirement Management
- D. Solution Manager Test Suite
Answer: A
NEW QUESTION 92
What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of SAP Activate?
Please choose the correct answer.
Response:
- A. Learning plan
- B. Project Documentation
- C. Knowledge transfer to end users
- D. Project Charter
Answer: A
NEW QUESTION 93
Which of the following will help you avoid modification of standard functionality in SAP S/4HANA Cloud, Single Tenant Edit on?
There are 3 correct answers to this question.
Response:
- A. A developer key
- B. Contract restrictions in SAP HANA Enterprise Cloud and SAP S/4HANA Cloud, Single Tenant Edition
- C. SAP Code Inspector
- D. The 5 Golden Rules
- E. The Side-by-Side Extensibility Option (such as SAP Cloud Platform)
Answer: B,D,E
NEW QUESTION 94
Which of the following content best outlines the scope of the Integration Test?
Please choose the correct answer.
Response:
- A. a. Prototype
b. Delta/gap solutions
c. Data flows with non-SAP application - B. a. Solution baseline
b. Delta configuration
c. Data flows between SAP solutions - C. a. Solution baseline
b. Delta/gap solutions
c. Data flows with non-SAP application - D. a. Prototype
b. Delta configuration
c. Data flows between SAP solutions
Answer: C
NEW QUESTION 95
Which of the following is not correct about workstreams?
There are 2 correct answers to this question.
Response:
- A. It is a collection of related deliverables
- B. Workstreams are dependent on phase start and end
- C. It is assigned as an attribute to phases, deliverables and tasks
- D. It can span phases
Answer: B,C
NEW QUESTION 96
Which Value Chains does SAP Solution Manager 7.2 deliver?
There are 3 correct answers to this question.
Response:
- A. Detect-to-Correct
- B. Cash-to-Order
- C. Requirements-to-Deploy
- D. Request-to-Fulfill
- E. Hire-to-Retire
Answer: A,C,D
NEW QUESTION 97
What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition?
Please choose the correct answer.
Response:
- A. SAP Best Practices
- B. Rapid prototyping
- C. Full project SCRUM
- D. Project team training
Answer: A
NEW QUESTION 98
What is the most granular level of the methodology you can view in the SAP Roadmap Viewer?
Please choose the correct answer.
Response:
- A. Scenario
- B. Phase
- C. Deliverables
- D. Task
Answer: D
NEW QUESTION 99
What are the responsibilities of the Product Owner in release and sprint planning?
There are 2 correct answers to this question.
Response:
- A. Estimate the backlog user stories.
- B. Prioritize backlog user stories by business priority.
- C. Analyze the functional and technical dependencies between the user stories.
- D. Define objectives for each release.
Answer: B,D
NEW QUESTION 100
Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition?
There are 3 correct answers to this question.
Response:
- A. Operations impact analysis
- B. Development system migration
- C. Sandbox system migration
- D. Custom code adjustment
- E. Delta configuration
Answer: B,D,E
NEW QUESTION 101
......
SAP C_ACTIVATE13 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Agile Project Planning 8% - 12% | Describe the agile project roles and responsibilities and the preparation of the project including the planning, estimation, user story mapping and construction of backlog |
| Transition Path "New Implementation SAP S/4HANA On Premise" < 8% | Describe concepts, landscape overview and specifics in Workstreams related to implementing SAP S/4HANA On Premise. |
| SAP Activate Elements > 12% | Provide an overview of content, tools and methodology elements of SAP Activate Solution Implementation Framework. Include Fit to Standard |
| Transition Path "Selective Data Transition" < 8% | Describe concepts, landscape overview and specifics in Workstreams related to “Selective Data Transition” Transition Path. |
| Workstreams Overview > 12% | Describe concepts, artefact flows, accelerators, tools and roles for each Workstream within SAP Activate Methodology |
| Transition Path "New Implementation SAP S/4HANA Cloud" 8% - 12% | Describe concepts, landscape overview, and specifics in Workstreams related to implementing SAP S/4HANA Cloud. |
| SAP Activate Overview > 12% | Define factors influencing SAP Activate, its purpose and place among other frameworks |
| Transition Path "System Conversion" < 8% | Describe concepts, landscape overview and specifics in Workstreams related to “System Conversion” Transition Path. |
| Agile Project Delivery > 12% | Describe how the project team prepares release and sprint plans, and the structure and key activities in each sprint. Discuss key techniques used in agile projects |